Molds for cement pavers are available in most large hardware stores.
Making your own stackable concrete pavers retaining wall.
In this video i showed how you can make your own concrete stacked stone at home.
If the wall runs up a hill continue each base course of stackable retaining wall blocks into the hill until the top of the second course is level with the grade and then start your second base course at that point.
Remember one mold makes only one cement paver and it will take at least two weeks before your cement paver is ready for use.
Whatever your choice do ensure that you have lots of molds.
Excavate to a depth of 6 inches along the entire base of the stone retaining wall using the string marker as a guide.
Adjust for sloping ground.
For row one knock off the flanges with a hammer and chisel so the.
If stacking pavers to retain soil and the wall is more than two feet high backfill a couple inches directly behind the wall with gravel.
For this project you will need.
With the layout marked you can begin digging the trench.
Dig for the first row of block.
For this 18 inch high wall the footing should be at least 18 inches wide.
The exact depth of the.
To bury the first row.
Place a perforated drainage pipe 2 inches up from ground.
If you have the option it can be easier to excavate and lay the lowest course before excavating the trench for the next step.
After you finish the first course fill the space between your retaining wall and.
If needed reposition it using additional.
Position your first block and use a standard level to make sure it s even.
Continue laying your first course of blocks making sure to check that every block is level.
Work gloves shovel and or mattock brick chisel and small sledgehammer level wooden stakes string and a line level soil tamper gravel sharp not rounded or rock dust landscape fabric optional interlocking stackable stones and toppers.
For a stacked block retaining wall that s no higher than four feet a trench filled with three inches of crushed rock will help keep the wall from shifting and settling.
Prepare the foundation step 1.
Use a hand or power tamper to level the base.